Project Management Professional Practice Question

Given a project with the following activities and durations:

  • Activity A (Duration: 3 days, depends on no other activity)
  • Activity B (Duration: 5 days, depends on Activity A)
  • Activity C (Duration: 2 days, depends on Activity A)
  • Activity D (Duration: 4 days, depends on Activity B and Activity C)

What is the Early Finish (EF) for Activity D?

  • 12 days

  • 9 days

  • 8 days

  • 11 days

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot