Project Management Professional Practice Question
In a cost-plus incentive fee contract, if the actual cost exceeds the Point of Total Assumption (PTA), the buyer bears all additional costs beyond this point.
False
True
In a cost-plus incentive fee contract, if the actual cost exceeds the Point of Total Assumption (PTA), the buyer bears all additional costs beyond this point.
False
True
The correct answer is False. The Point of Total Assumption (PTA) is the cost at which the seller assumes all additional costs beyond this point, not the buyer. When the actual cost exceeds the PTA, the seller's profit is reduced by the full amount of any additional costs. This is a crucial concept in cost-plus contracts as it represents the point where the risk shifts entirely to the seller. Understanding the PTA helps project managers and contractors better assess and manage financial risks in these types of contracts.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.