In a project, Activity B is dependent on the completion of Activity A. If Activity A has an Early Finish (EF) of Day 5 and Activity B has a duration of 3 days, what is the Early Start (ES) of Activity B?
The Early Start (ES) of an activity in CPM is determined by the Early Finish (EF) of its predecessor. Since Activity B depends on the completion of Activity A which finishes on Day 5, Activity B can start the next day. Therefore, the ES of Activity B is Day 6. Calculating ES involves recognizing that an activity's early start is the earliest time its dependencies allow it to begin.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What does EF stand for in project management?
Open an interactive chat with Bash
What is the significance of dependencies in project management?
Open an interactive chat with Bash
Can you explain the Critical Path Method (CPM)?
Open an interactive chat with Bash
Project Management Professional
People
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access