In a project with 6 stakeholders, there are 15 potential communication channels.
True
False
Project Management Professional
Process
Your Score:
Bash, the Crucial Exams Chat Bot
AI Bot
In a project with 6 stakeholders, there are 15 potential communication channels.
True
False
This statement is true. The number of communication channels is calculated using the formula N(N-1)/2, where N is the number of stakeholders. In this case:
6(6-1)/2 = 6(5)/2 = 30/2 = 15
Understanding this formula is important for project managers because it helps them anticipate the complexity of communications as the number of stakeholders increases. This knowledge aids in developing effective communication strategies, allocating resources for communication management, and maintaining efficient information flow throughout the project.
It's worth noting that if the number of stakeholders were to increase by just one (to 7), the number of communication channels would jump to 21, demonstrating how quickly communication complexity can grow in projects with many stakeholders.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.