Project Management Professional Practice Question
In PERT analysis, if the pessimistic estimate for an activity is 25 days and the optimistic estimate is 13 days, the standard deviation is 3 days.
False
True
In PERT analysis, if the pessimistic estimate for an activity is 25 days and the optimistic estimate is 13 days, the standard deviation is 3 days.
False
True
The statement is false. The correct standard deviation is 2 days. In PERT analysis, the standard deviation (σ) is calculated using the formula: σ = (Pessimistic - Optimistic) / 6. In this case, (25 - 13) / 6 = 12 / 6 = 2 days. This value represents the variability or uncertainty in the activity duration estimate. Project managers use this information to assess the risk associated with activity durations and to calculate the probability of completing the project within a specific timeframe. Understanding how to correctly calculate the standard deviation is crucial for accurate risk assessment and project planning.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.