On a construction project, if the Late Start (LS) for the installation of fixtures is scheduled for day 25 and is expected to take 10 days, what is the Late Finish (LF) for this activity?
Late Finish (LF) is calculated by adding the duration of the activity to the Late Start (LS). With a Late Start (LS) on day 25 and an installation activity duration of 10 days, the Late Finish (LF) would be: LF = LS + Duration, which results in LF = 25 + 10, so LF is day 35.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is Late Start (LS) in project management?
Open an interactive chat with Bash
How do you calculate Late Finish (LF) more generally in project management?
Open an interactive chat with Bash
What is the significance of knowing Late Finish (LF) in a construction project?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access