The project manager for an infrastructure development project is preparing for an upcoming major deliverable review. The deliverable has to meet specific regulatory standards and customer quality requirements. Which of the following would be the MOST appropriate for the project manager to ensure that the deliverable is compliant and ready for the review?
Consult the quality metrics to verify that the deliverable adheres to defined quality standards.
Assess the impact of all approved change requests on the project's quality management plan.
Analyze the latest quality reports to determine if the deliverables are functioning as intended.
Review the latest project management plan updates to check for any quality-related adjustments.
Reviewing quality metrics is the most appropriate action for the project manager as it specifically describes how project deliverables will verify compliance with quality standards as part of quality control processes. Quality reports and lessons learned could provide insights, but are not directly focused on compliance of a specific deliverable. Approved change requests could impact the quality control process but they pertain to modifications on project work, not assessing compliance of a completed deliverable.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are quality metrics in project management?
Open an interactive chat with Bash
What is the role of the quality management plan in a project?
Open an interactive chat with Bash
How do change requests impact project quality?
Open an interactive chat with Bash
Project Management Professional
Waterfall
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access