What is the primary function of establishing escalation paths and thresholds within a project governance structure?

  • To track the performance of team members and manage evaluations

  • To reduce the overall risks associated with the project by involving senior management

  • To directly resolve resource constraints and allocate additional resources effectively

  • To ensure that issues are addressed by the appropriate level of management at the correct time

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot