Project Management Professional Practice Question

Which of the following best describes how the project schedule is typically prepared in an Agile project methodology?

  • The project manager creates a detailed Gantt chart with all tasks and dependencies at the beginning of the project.

  • The project sponsor provides a fixed schedule that the team must adhere to throughout the project.

  • The team works in short iterations, planning and scheduling work for each iteration separately.

  • The project schedule is prepared using the critical path method, identifying the longest sequence of tasks.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot