Project Management Professional Practice Question

You are managing a software development project that involves creating a new application. Your team has identified an activity 'Design User Interface' that typically takes 10 days. However, you've recently learned that one of your most experienced designers will be unavailable for the first 5 days. How should this impact your estimation for 'Design User Interface' duration if your team will have a new, less experienced designer during those 5 days?

  • Decrease the duration estimate to 7 days as an average between the experienced and less experienced designers.

  • Increase the duration estimate to 15 days to account for the reduced productivity of the less experienced designer.

  • Reset the duration estimate to 5 days based on the availability of the less experienced designer.

  • Keep the duration estimate at 10 days since the team has already performed similar tasks within this timeframe.

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot