00:15:00

CompTIA Project+ Practice Test (PK0-005)

Use the form below to configure your CompTIA Project+ Practice Test (PK0-005). The practice test can be configured to only include certain exam objectives and domains. You can choose between 5-100 questions and set a time limit.

Logo for CompTIA Project+ PK0-005
Questions
Number of questions in the practice test
Free users are limited to 20 questions, upgrade to unlimited
Seconds Per Question
Determines how long you have to finish the practice test
Exam Objectives
Which exam objectives should be included in the practice test

CompTIA Project+ PK0-005 Information

The CompTIA Project+ certification is a globally recognized credential designed for professionals who manage small to medium-sized projects. Unlike more specialized project management certifications, Project+ provides a broad foundation, making it an ideal starting point for individuals who are new to project management or who manage projects alongside other job responsibilities. It covers essential concepts such as project life cycles, roles and responsibilities, communication strategies, and risk management. Because it does not require extensive prior experience or prerequisites, it is often seen as a practical alternative to more complex certifications like the PMP, offering a straightforward way for professionals to validate their project management knowledge.

One of the key advantages of CompTIA Project+ is its flexibility across industries. While many project management certifications are heavily focused on IT, Project+ applies to a wide range of business environments, including healthcare, finance, and manufacturing. This makes it especially useful for professionals who may not be strictly in the IT field but still need to understand and manage projects effectively. Employers value Project+ because it demonstrates a candidate’s ability to lead projects, manage resources, and ensure that deliverables meet business objectives. Additionally, it helps bridge the gap between technical teams and stakeholders, fostering better communication and coordination throughout a project's life cycle.

For those looking to advance their careers, CompTIA Project+ serves as a valuable stepping stone to more advanced project management certifications. It provides a solid understanding of fundamental project management principles, which can be built upon with further training and experience. Many professionals who earn Project+ go on to pursue certifications like PMP or PRINCE2, leveraging their foundational knowledge to handle more complex projects. Furthermore, because CompTIA certifications are vendor-neutral, Project+ holders are not tied to any specific project management methodology, giving them the flexibility to adapt to different organizational needs. With a growing emphasis on project-based work across industries, earning Project+ can provide professionals with a competitive edge in the job market.

Free CompTIA Project+ PK0-005 Practice Test

Press start when you are ready, or press Change to modify any settings for the practice test.

  • Questions: 15
  • Time: Unlimited
  • Included Topics:
    Project Management Concepts
    Project Life Cycle Phases
    Tools and Documentation
    Basics of IT and Governance

Free Preview

This test is a free preview, no account required.
Subscribe to unlock all content, keep track of your scores, and access AI features!

Question 1 of 15

Which type of chart displays project tasks along a timeline, illustrating their start and end dates as well as task dependencies?

  • Budget burndown chart

  • Gantt chart

  • PERT chart

  • Milestone chart

Question 2 of 15

A company must choose between two projects. Project Alpha will cost $200,000 and is expected to generate $300,000 in revenue. Project Beta will cost $150,000 and is expected to generate $250,000 in revenue. Which project provides a higher percentage return on the initial investment?

  • Project Beta provides a higher percentage return

  • Cannot determine from the information given

  • Both projects have the same percentage return

  • Project Alpha provides a higher percentage return

Question 3 of 15

Consideration of a project's impact on a company's brand value is unnecessary during project management activities.

  • False

  • True

Question 4 of 15

A Gantt chart displays project tasks, their durations, and the dependencies between tasks over a timeline.

  • True

  • False

Question 5 of 15

As a project manager overseeing the development of a new manufacturing facility, you need to ensure the project minimizes negative effects on the local community and aligns with global sustainability practices. Which of the following actions would BEST achieve this goal?

  • Ignore local regulations to expedite the project timeline.

  • Prioritize cost-saving measures over environmental considerations.

  • Schedule environmental impact assessments after construction.

  • Incorporate renewable energy sources into the facility's design.

Question 6 of 15

A project team is having difficulty understanding the sequence of activities and their durations within a project. The project manager decides to provide a visual representation that shows tasks over time, including their start and end dates and how they overlap. Which of the following tools should the project manager use to assist the team?

  • Fishbone diagram

  • Risk report

  • Gantt chart

  • Issue log

Question 7 of 15

A company is launching a new project and has already selected the recipient of the project's deliverables before initiation. What is this scenario called?

  • Potential client

  • Prequalified vendor

  • Predetermined client

  • Open procurement

Question 8 of 15

A project manager wants to engage suppliers who have been evaluated and approved before the project begins to ensure they meet specific criteria. What type of suppliers are these?

  • Certified vendors

  • Preferred vendors

  • Prequalified vendors

  • Single-source vendors

Question 9 of 15

A business case is used to justify a project's initiation by evaluating its potential benefits, costs, and risks during the discovery phase.

  • False

  • True

Question 10 of 15

During the discovery phase, a project manager analyzes expenses used to acquire or upgrade physical assets such as equipment. What type of expenses are these?

  • Administrative Expenses

  • Capital Expenses

  • Variable Expenses

  • Operational Expenses

Question 11 of 15

As a project manager overseeing a project with a strict budget, you need to monitor and display the amount of budget consumed versus the amount remaining over time to ensure the project stays within financial constraints. Which tracking chart would be most appropriate for this purpose?

  • Earned value chart

  • Budget burndown chart

  • Gantt chart

  • Milestone chart

Question 12 of 15

A project manager needs to determine the sequence of activities and identify task dependencies to calculate the critical path of the project. Which of the following tools would BEST help achieve this goal?

  • Gantt chart

  • Project network diagram

  • Milestone chart

  • Budget burndown chart

Question 13 of 15

A project manager is overseeing a project that involves deploying wireless networking equipment in multiple facilities. To ensure compliance with local regulations, which of the following should the project manager prioritize?

  • Ensure equipment is purchased from preferred vendors.

  • Select equipment based on cost savings.

  • Rely on the network engineers to handle any compliance issues.

  • Verify equipment complies with regional radio frequency regulations.

Question 14 of 15

A project manager needs to determine the necessary steps to transition from the organization's existing operations to the improved operations envisioned by the project. Which of the following should the project manager perform to identify the required changes?

  • Conduct a gap analysis

  • Develop a project charter

  • Create a stakeholder register

  • Perform a needs assessment

Question 15 of 15

Which document is used to track problems that arise during a project, ensuring they are addressed and resolved?

  • Project dashboard

  • Risk register

  • Issue log

  • Change log