00:15:00

CAPM Practice Test

Certified Associate in Project Management

Use the form below to configure your CAPM Practice Test. The practice test can be configured to only include certain exam objectives and domains. You can choose between 5-100 questions and set a time limit.

Logo for CAPM
Questions
Number of questions in the practice test
Free users are limited to 20 questions, upgrade to unlimited
Seconds Per Question
Determines how long you have to finish the practice test
Exam Objectives
Which exam objectives should be included in the practice test

CAPM Information

The Certified Associate in Project Management (CAPM) is a certification offered by the Project Management Institute (PMI). It is designed for people who are new to project management or those who want to learn about managing projects. The CAPM helps you show that you understand the basics of project management and are ready to work on project teams.

The CAPM is an entry-level certification, which means you don’t need years of experience to take it. To be eligible, you need a high school diploma or an equivalent degree, such as an associate degree. You also need to complete at least 23 hours of project management education. These hours can come from classes or training programs that focus on project management skills and concepts.

The CAPM exam is 3 hours long and includes 150 multiple-choice questions. The test covers key areas of project management, such as planning, scheduling, budgeting, and risk management. It is based on the PMI’s “Project Management Body of Knowledge” (PMBOK Guide), which is a book that explains the best practices and techniques for managing projects. Studying the PMBOK Guide is important to prepare for the exam.

Having a CAPM certification shows that you know the tools and processes needed to help projects succeed. This can make you a stronger candidate when applying for jobs. Many employers look for people who understand project management, even if they are just starting their careers. The CAPM can also help you stand out among other applicants.

The CAPM is valid for three years. After that, you can renew it by earning Professional Development Units (PDUs). PDUs are earned by learning more about project management or doing related activities, such as taking courses or attending workshops. This helps you stay up to date on new practices and keep your skills sharp.

The CAPM is useful in many industries, like construction, healthcare, technology, and more. Any job that involves managing tasks, teams, or deadlines can benefit from project management knowledge. Even if you are not a manager, understanding how projects work can help you contribute better to your team.

Getting the CAPM certification is a great way to start your journey in project management. It shows that you are serious about learning and growing in this field. While it is not required to have a CAPM to become a project manager, it can help you get there faster by building your confidence and knowledge.

Overall, the CAPM is a simple and effective way to learn the basics of project management and open doors to new career opportunities. Whether you are a student, someone changing careers, or just starting out, the CAPM is a step in the right direction. It gives you the foundation you need to understand how projects are run and how you can be a valuable part of a team.

Free CAPM Practice Test

Press start when you are ready, or press Change to modify any settings for the practice test.

  • Questions: 15
  • Time: Unlimited
  • Included Topics:
    Project Management Fundamentals and Core Concepts
    Predictive, Plan-Based Methodologies
    Agile Frameworks/Methodologies
    Business Analysis Frameworks

Free Preview

This test is a free preview, no account required.
Subscribe to unlock all content, keep track of your scores, and access AI features!

Question 1 of 15

A company is undertaking several related initiatives aimed at launching a new product line. These initiatives include product development, marketing campaigns, supply chain setup, and customer service training. The company wants to manage these initiatives collectively to ensure alignment with overall goals and to maximize benefits.

How should the company best categorize these efforts to manage them effectively?

  • Include them in the company's portfolio.

  • Treat them as operational activities.

  • Group them into a program.

  • Manage them as separate projects.

Question 2 of 15

Which of the following is best described as a group of related projects managed in a coordinated way to obtain benefits not available from managing them individually?

  • Portfolio

  • Project

  • Operation

  • Program

Question 3 of 15

As a project manager, you discover that a team member has intentionally falsified test results to meet a project deadline. According to the PMI Code of Ethics and Professional Conduct, what is the most appropriate action for you to take?

  • Remove the team member from the project

  • Report the issue at the end of the project to to keep on schedule

  • Confront the team member privately before involving others

  • Report the team member's actions to appropriate management and take corrective action

Question 4 of 15

In project scheduling, the critical path is the shortest sequence of activities that determines the minimum project duration.

  • True

  • False

Question 5 of 15

Creating the project schedule is an activity performed during the project executing process.

  • True

  • False

Question 6 of 15

A project manager is assigned to oversee the construction of a new office building for a client. The project has a fixed budget, a strict deadline, and well-defined requirements. The organization has a hierarchical structure with established processes and procedures. Given these factors, which methodology should the project manager use?

  • A hybrid methodology

  • A predictive, plan-driven methodology

  • An agile methodology

  • An adaptive methodology

Question 7 of 15

Which statement BEST distinguishes a project from operations within an organization?

  • Projects are temporary initiatives with specific goals, while operations are continuous activities that keep the organization running.

  • Projects do not require management oversight, but operations are carefully managed.

  • Projects are confined to specific departments, while operations span the entire organization.

  • Projects involve routine tasks, whereas operations focus on creating unique products or services.

Question 8 of 15

During a project, the manager evaluates how the project's progress compares to the plan and implements actions to address any deviations. Which activity is the manager typically performing?

  • Measuring project performance

  • Releasing project resources

  • Conducting team-building activities

  • Creating a communication plan

Question 9 of 15

Which document provides the project manager with authority to utilize organizational resources for project activities?

  • Project Charter

  • Project Management Plan

  • Organizational Process Assets

  • Project Scope Statement

Question 10 of 15

Predictive, plan-based project management approaches are well-suited for projects within a hierarchical organizational structure.

  • False

  • True

Question 11 of 15

How does a project enable an organization to implement new strategies or transformations?

  • By managing routine operations that keep current processes running smoothly

  • By ensuring existing procedures are replicated without changes to maintain consistency

  • By focusing on standard tasks that do not introduce any new elements to the organization

  • By initiating a temporary effort to create unique outcomes that support strategic objectives

Question 12 of 15

During project planning, a project manager compiles a document that lists potential events that could impact the project, along with their probabilities and impacts. This document also includes the response strategies for each identified event. What is this document called?

  • Risk register

  • Issue log

  • Stakeholder register

  • Change log

Question 13 of 15

When critiquing a project's scope, what should be the primary focus to ensure successful project outcomes?

  • Confirming the project team has necessary skills and training.

  • Assessing potential risks and developing mitigation plans.

  • Verifying that project costs are within the allocated budget.

  • Ensuring the work required is clearly defined and agreed upon by stakeholders.

Question 14 of 15

You are managing a project with a fixed scope, stable requirements, and a clear schedule. Stakeholders have agreed on all specifications, and changes are unlikely to occur. Which methodology is most appropriate for this project?

  • Adaptive methodology

  • Predictive methodology

  • Incremental methodology

  • Iterative methodology

Question 15 of 15

During a project meeting, a team member mentions that a key supplier has gone out of business, affecting the project's timeline. This situation is an example of a(n):

  • Issue

  • Constraint

  • Risk

  • Assumption